API 570 Piping Inspector Practice Questions — 10 Free (2026)

Answer them, then check the reasoning and the clause each one comes from. No account, no card, nothing to dismiss. New to the exam? Read the exam guide.

6 CLOSED BOOK4 OPEN BOOK8 STANDARDS

API 570 exam at a glance

Questions
170 in total: 140 scored and 30 unscored pretest questions
Split
110 closed-book, 60 open-book
Exam day
7.5 hours: a short tutorial, 2.75 hours closed-book, a 45-minute lunch break, 3.75 hours open-book
Delivery
Computer-based, in person at Prometric test centres
Open-book references
PDFs of the relevant codes and standards are provided on screen, in English
Results
Score report from Prometric by email within 24 hours; final result in the API ICP portal within 3 business days
Retake
Not in the same exam window — book the next window
Certification
API 570 certification is valid for three years, then recertification

The ten questions below draw on API 577, ASME PCC-2, API 574, ASME V, API 571, ASME IX, ASME B31 3 and API 570.

Exam facts checked against the awarding body’s own documents, 16 September 2026. Full exam guide.

Common questions

Do I need an account to try these?
No. The ten questions on this page are open to anyone — no registration, no card. An account is only needed for the full bank.
What does “the clause it comes from” mean?
Every answer names the publication and the paragraph the rule sits in, so you can find it in your own copy rather than taking our word for it. That is the habit the open-book part of these exams rewards.
How large is the full API 570 bank?
5,261 questions, including 10 full-length mock papers, with 432 figures and exhibits.
Only the first answer counts — why?
In study mode a question you have already seen the key for cannot improve your record. It keeps the progress figures, and the certificate they lead to, worth something.
Which editions are examinable for API 570?
The publications in force, and which sections are examined, are listed in the exam guide — taken from the awarding body's own effectivity documents and checked 16 September 2026.
Is AssetronX affiliated with the certifying body?
No. AssetronX is an independent examination-preparation provider and is not affiliated with, endorsed by or accredited by any certifying body. The questions are our own; the publications they refer to are not.
10 QUESTIONS
CLOSED BOOKAPI 5771 / 10

Which document must be reviewed by the inspector to ensure the welder has undergone the proper testing to perform a specific production weld?

Worked answers

All ten API 570 Piping Inspector questions with the correct option, why it is correct and the paragraph it comes from. Attempt them above first — the reasoning is worth more than the key.

Show the ten answers and their references
  1. Q1  ·  API 577  ·  Closed book

    Which document must be reviewed by the inspector to ensure the welder has undergone the proper testing to perform a specific production weld?

    • A. WPS
    • B. PQR
    • C. WPQ ✓
    • D. MTR
    • E. NDE Report

    The Welder Performance Qualification (WPQ) is reviewed to ensure that the individual welder has been properly tested and is qualified to perform work according to a specific WPS. API 577, 9.2.1.1

  2. Q2  ·  ASME PCC-2  ·  Closed book

    Because the phenomena involved are irreversible, de-embrittlement does not apply to which degradation type?

    • A. Temper embrittlement
    • B. Hydrogen embrittlement
    • C. Hydrogen attack ✓
    • D. Both A and B
    • E. None of the above

    Hydrogen attack and creep embrittlement involve irreversible damage, making de-embrittlement ineffective. ASME_PCC2, Table 215-4.5-1

  3. Q3  ·  API 574  ·  Closed book

    Consistent with the API inspection approach referenced by API 574, the next thickness inspection interval is set as the lesser of the maximum period or:

    • A. The full remaining life
    • B. One-half the remaining life ✓
    • C. One-quarter the remaining life
    • D. Twice the remaining life
    • E. Three-quarters the remaining life

    Thickness intervals are typically the lesser of the code maximum or one-half the remaining life; API 574 defers the interval rules to API 570. API RP 574 (defers intervals to API 570)

  4. Q4  ·  ASME V  ·  Closed book

    T-741.2 sets what requirement when the surface contrast enhancement used is nonmagnetic?

    • A. Thickness must be measured
    • B. It must be removed before testing and the surface re-cleaned
    • C. It must be demonstrated that indications can be detected ✓
    • D. It must be applied with a brush
    • E. It must be fluorescent

    When using contrast enhancement, it must be demonstrated that indications are still detectable through it. ASME Section V T-741.2

  5. Q5  ·  API 571  ·  Closed book

    In condensate systems, ammonia (with oxygen) specifically tends to attack:

    • A. Carbon steel far more than any copper alloy under typical refinery operating conditions
    • B. Only austenitic stainless steel
    • C. Only titanium components in the system
    • D. Copper-based alloys such as admiralty brass ✓
    • E. Only aluminum ducting downstream

    Ammonia (with oxygen) preferentially attacks copper alloys (e.g., admiralty brass) in condensers/condensate systems. The other statements are incorrect. API 571, Boiler Water and Steam Condensate Corrosion

  6. Q6  ·  ASME IX  ·  Closed book

    What is considered an essential variable requiring requalification?

    • A. Change in welding process ✓
    • B. Change in filler metal diameter
    • C. Change in groove angle
    • D. Change in backing composition
    • E. Change in preheat temperature

    Switching the welding process is treated as an essential variable, so the procedure must be requalified. ASME IX, QW‑401

  7. Q7  ·  ASME IX  ·  Open book

    Review Exhibit WPS-PQR-05. Considering the thickness of the PQR test coupon, what maximum base metal thickness does the qualification actually support, and is the range stated on the WPS acceptable?

    • A. 0.75 in. maximum
    • B. 8.000 in. maximum
    • C. 1.5 in. maximum ✓
    • D. 3 in. maximum
    • E. 0.998 in. maximum

    The coupon is 0.75 in., so the maximum base metal thickness qualified is 1.5 in. The WPS claims 3 in., which the PQR does not support, so the range is not acceptable as written. Both ends of a stated range must be checked independently; the lower end is correct here. ASME BPVC Section IX, Table QW-451.1

  8. Q8  ·  ASME B31 3  ·  Open book

    A pipe in A106 Grade B with an outside diameter of 3.5 in. (88.9 mm) is designed for 1100 psig at 500 deg F. The longitudinal weld joint quality factor is 1, W = 1.0 and Y = 0.4. What is the pressure design thickness for internal pressure?

    • A. 0.111 in. (2.83 mm)
    • B. 0.088 in. (2.22 mm)
    • C. 0.102 in. (2.59 mm)
    • D. 0.1 in. (2.53 mm) ✓
    • E. 0.2 in. (2.53 mm)

    A106 Grade B gives 18,900 psi at 500 deg F. Applying t = PD/(2(SEW + PY)) gives 0.1 in. (2.53 mm). Dropping the PY term from the denominator is the most frequent error, and taking E as 1.0 when the pipe is welded credits a seamless product that was not supplied. ASME B31.3, 304.1.2, Appendix A and Table A-1C

  9. Q9  ·  API 570  ·  Open book

    A buried line runs through soil measured at 1,500 ohm-cm. What is the recommended maximum interval for alternate pressure test with effective cathodic protection?

    • A. 10 years
    • B. 2.5 years
    • C. 7.5 years
    • D. 15 years
    • E. 5 years ✓

    Table 4 is entered on soil resistivity. For this band the alternate pressure test with effective cathodic protection interval is 5 years. The three interval columns in each row differ, so selecting the wrong column is the standard error; the unprotected pressure test interval is always half the protected one. API 570, Table 4

  10. Q10  ·  ASME PCC-2  ·  Open book

    As per ASME PCC-2, a repair is being designed on a component with a nominal wall thickness of 0.437 in. (11.1 mm). What is the minimum recommended thickness of a Type A sleeve?

    • A. 0.328 in. (8.32 mm)
    • B. 0.437 in. (11.1 mm)
    • C. 0.291 in. (7.4 mm) ✓
    • D. 0.218 in. (5.55 mm)
    • E. 0.874 in. (22.2 mm)

    Two-thirds of the carrier pipe thickness is the minimum for a Type A sleeve. Its ends receive no circumferential weld to the carrier pipe, so it reinforces the defect without being able to hold pressure. That works out to 0.291 in. (7.4 mm) here. ASME PCC-2, 206-3.1

5,261 more like these

Plus 10 full-length mock exams in the two-section shape of the real day, study mode with instant feedback, and timed practice.

Other certifications in this family

AssetronX is an independent examination-preparation provider, not affiliated with, endorsed by or accredited by API, AMPP, NACE, ASNT, CSWIP, IASSC, SHRM, PMI, CIPS or any certifying body. Questions are our own work; the publications they refer to are not.